Frankfurt (Germany), 6-9 June 2011
MMininiimum short circuit power in the LV mum short circuit power in the LV distribution network to meet EN 50160 distribution network to meet EN 50160 standard requirements standard requirements
David MEZERA [email protected]
Martin KAŠPÍREK [email protected]
E.ON Czech Republic – Czech Republic
Frankfurt (Germany), 6-9 June 2011
This investigation was done on the basis of: 8 years experience of PQ measurement Evaluated over 3000 measurements PQ in the LV network The LV network contains of
18.005 MV/LV distribution substation [piece] 21.660 LV cable underground line [km] 17.151 LV overhead line [km]
Real LV network was monitored for a long time on 3.000 different PCC
The sources of this survey
Frankfurt (Germany), 6-9 June 2011
The final result of 3.000 measurements PQ
Frankfurt (Germany), 6-9 June 2011
Who is responsible?
DNO Pure network=low short circuit power (Sk)? Badly connected customers?
Customers Using of nonstandard apparatus? Electric apparatus?
Frankfurt (Germany), 6-9 June 2011
Minimum short circuit power LV
Thanks to IEC 725 we can set the reference impedance value, or more precisely, a relative short circuit power value for the LV distribution network and electric equipment of nominal current less than 16/75 A
Electric equipment with nominal current
Reference short circuit impedance
[Ω]
Reference short circuit power [kVA]
up to 16A 0,28 570
up to 75A 0,21 760
Frankfurt (Germany), 6-9 June 2011
Relation: short circuit power X PQ
Frankfurt (Germany), 6-9 June 2011
Relation: short circuit power X PQ
Frankfurt (Germany), 6-9 June 2011
Relation: short circuit power X PQ
Frankfurt (Germany), 6-9 June 2011
Relation: short circuit power X PQ
Frankfurt (Germany), 6-9 June 2011
Conclusions for DNO
To connect the new appliances according to Sk in the LV network
To increase Sk above minimum Sk 760 kVA, (900 kVA is recommended for today real used electric appliances) To increase the cross-section of existing LV overhead lines To build new MV/LV substations
Frankfurt (Germany), 6-9 June 2011
To increase the cross-section of the existing LV overhead lines
To increase the cross-section of the existing LV overhead lines not realizable
Frankfurt (Germany), 6-9 June 2011
To build new MV/LV substations
The final calculation is: 54% new substations. This accounts for a construction of
9723 new substations, including transformers and MV connection with approximate total investment cost of:
EUR 280 million.
Frankfurt (Germany), 6-9 June 2011
Conclusion
The pure PQ in LV network is caused by poor conditions on both sides, DNO and customer. Solution on the side of DNO is calculated on 280
million EUR. Solution on the side of customers ??